World's Largest Fusion Reactor Delayed Again to 2039
The ITER Council has revised the project's baseline schedule, pushing first plasma to 2035 and full deuterium-tritium operations to 2039, citing significant manufacturing and assembly challenges with key tokamak components.
The international ITER project has formally announced a significant schedule revision, delaying the start of full power operations by at least four years. In a recent update, the ITER Council confirmed that the new target for achieving first plasma is now 2035, a decade later than the 2025 date established in the previous baseline. Consequently, the commencement of deuterium-tritium (D-T) fuel cycle operations, the phase intended to demonstrate net energy gain, is now projected for 2039. The revised timeline is a direct result of critical component issues, primarily dimensional non-conformance in vacuum vessel sectors and the discovery of stress corrosion cracking in thermal shield cooling pipes. These setbacks necessitate extensive on-site repairs and adjustments to the assembly sequence, fundamentally altering the project's critical path. Source: ITER
The technical challenges stem from two primary systems. First, inspections revealed that the welding of the nine massive vacuum vessel sectors, manufactured by consortia in Europe and Korea, resulted in dimensional deviations outside of specified tolerances. This requires complex on-site machining and realignment to ensure proper fit-up within the cryostat. Second, stress corrosion cracking and coolant leaks were discovered in the thermal shield cooling pipes, a system critical for managing heat loads between the 4K superconducting magnets and the 80K cryostat. The repair strategy for the thermal shield involves replacing affected sections, a delicate and time-consuming process given the component's location and the clean-room conditions required for assembly. These repairs must be completed before the tokamak pit can be sealed. Source: ITER
This requires complex on-site machining and realignment to ensure proper fit-up within the cryostat.
This latest revision represents the most significant delay since the project's 2016 baseline was established, which had set the 2025 first plasma target. The new schedule, championed by Director-General Pietro Barabaschi, is intended to provide a more realistic and technically achievable path forward, integrating the known repair timelines rather than deferring them. The delay underscores the immense engineering complexity of constructing a first-of-a-kind, industrial-scale tokamak. While the project has achieved major milestones, including the completion of the central solenoid and the arrival of all toroidal field coil magnets, the integration and assembly phase has proven to be a persistent bottleneck, highlighting the gap between component manufacturing and successful system integration at an unprecedented scale. Source: ITER
The updated timeline has broad implications for the global fusion energy roadmap. ITER's primary mission is to inform the design of subsequent demonstration power plants (DEMOs), and a delay to 2039 for full D-T operations pushes the timeline for collecting critical data on plasma physics, materials science, and tritium breeding well into the 2040s. This may increase pressure on the burgeoning private fusion sector and other national programs to demonstrate alternative or faster pathways to commercial fusion energy. The delay also adds to budgetary pressures for the seven member nations, although a revised cost-to-completion estimate has not yet been formally approved by the ITER Council. The focus now shifts to executing the complex repair plan and re-optimizing the assembly workflow to mitigate further schedule slippage. Source: ITER
Reporting grounded in coverage from the original publisher — read the source .
Weekly newsletter
Fusion Energy Weekly
The week in fusion: breakthroughs, companies, and capital — in your inbox. Free, every Monday.
Primary sources
Editorial standards: Fusion Energy News dispatches are compiled from primary filings, peer-reviewed papers, and on-the-record statements. Corrections: corrections@fusionenergynews.com · public log
More on Policy
Letters to the editor(0)
Sign in to write a letterNo letters yet. Be the first to write one.